Australia (en_GB)

Search results for "". Page 1 of 1, Results 1 to 16 of 16
Title Location Date Sort descending
Reset
Mine Geologist - Sunrise Dam AU 21 Dec 2024
Technician: Geology - Tropicana - 12 Month Fixed Term AU 17 Dec 2024
Specialist: Site Mobilisation Support
Specialist: Site Mobilisation Support AU Human Resources Support Services
AU 15 Dec 2024
Senior Engineer: Short-Term Planning AU 12 Dec 2024
Specialist: SC Improvement & Governance
Specialist: SC Improvement & Governance AU SCM Strategy & Planning
AU 6 Dec 2024
Senior Manager: Mining
Senior Manager: Mining AU Mine Planning
AU 6 Dec 2024
Manager: Environment Approvals & Closure
Manager: Environment Approvals & Closure AU Env Approvals & Closures
AU 5 Dec 2024
Senior Mine Geologist
Senior Mine Geologist AU Mine Geology
AU 5 Dec 2024
Technician: Electrical Maintenance - Sunrise Dam AU 4 Dec 2024
Day Operator: Processing - Sunrise Dam
Day Operator: Processing - Sunrise Dam AU Metallurgical Operations
AU 27 Nov 2024
Shutdown Planner/Scheduler: Maintenance - Tropicana AU 27 Nov 2024
Technician: Mechanical Maintenance - Sunrise Dam AU 27 Nov 2024
Water Treatment Specialist - NPI - Tropicana
Water Treatment Specialist - NPI - Tropicana AU Metallurgical Operations
AU 26 Nov 2024
Geological Production Assistant OP - Sunrise Dam AU 25 Nov 2024
Process Technician - Sunrise Dam
Process Technician - Sunrise Dam AU Technical & Project Support
AU 8 Nov 2024
UG Mining Manager
UG Mining Manager AU Mine Planning
AU 8 Nov 2024

AUSTRALIA

Australia hosts two of our operations – Sunrise Dam and Tropicana, both in the north-eastern goldfields in the state of Western Australia. Sunrise Dam is wholly owned, and includes our 70% interest in the Butcher Well project. We have a 70% holding in and manage Tropicana. Regis Resources Ltd holds the balance of 30% which it acquired from IGO Ltd on 31 March 2021.

AUSTRALIA

Australia hosts two of our operations – Sunrise Dam and Tropicana, both in the north-eastern goldfields in the state of Western Australia. Sunrise Dam is wholly owned, and includes our 70% interest in the Butcher Well project. We have a 70% holding in and manage Tropicana. Regis Resources Ltd holds the balance of 30% which it acquired from IGO Ltd on 31 March 2021.

Sunrise Dam

Sunrise Dam is an underground and open pit operation located 220km northeast of Kalgoorlie and 55km south of Laverton.

Overview and Locality

Underground mining, carried out by Barminco under an alliance contract, is now the primary source of ore, following the cessation of mining in the open pit in 2014. The underground mine produces approximately 2.7Mt of ore annually, which is supplemented by low-grade stockpiles generated during open cut mining to fill the processing plant.

Ore from the Golden Delicious open pit, 12 km from the processing plant, will contribute approximately 1Mt of ore annually for several years to displace some of the stockpiled material from mill feed. Surface infrastructure in place includes the site’s gas-fired power station, sealed airstrip, accommodation village, Central Tailings Discharge facility and workshops

The 4.1 Mtpa processing plant comprises conventional gravity and CIL circuits and a flotation/fine grind circuit. A major multi-year underground exploration programme underway at the site has identified extensions to known mineralisation and several significant new ore zones.

 

A Brief History

Open pit production began in 1997 and the main pit was completed at a final depth of 500m below surface in 2014. Underground mining started in 2003 with a number of different mining methods being applied, depending on the style of mineralisation and grade of the geological domain.

Installation of a new fine grind and flotation circuit was completed in the second half of 2018. In 2021, mining commenced at the Golden Delicious satellite pit using open cut mining methods. A new higher-grade and shallower orebody, Frankie, was accessed by year-end 2021

Overview and Locality

Underground mining, carried out by Barminco under an alliance contract, is now the primary source of ore, following the cessation of mining in the open pit in 2014. The underground mine produces approximately 2.7Mt of ore annually, which is supplemented by low-grade stockpiles generated during open cut mining to fill the processing plant.

Ore from the Golden Delicious open pit, 12 km from the processing plant, will contribute approximately 1Mt of ore annually for several years to displace some of the stockpiled material from mill feed. Surface infrastructure in place includes the site’s gas-fired power station, sealed airstrip, accommodation village, Central Tailings Discharge facility and workshops

The 4.1 Mtpa processing plant comprises conventional gravity and CIL circuits and a flotation/fine grind circuit. A major multi-year underground exploration programme underway at the site has identified extensions to known mineralisation and several significant new ore zones.

A Brief History

Open pit production began in 1997 and the main pit was completed at a final depth of 500m below surface in 2014. Underground mining started in 2003 with a number of different mining methods being applied, depending on the style of mineralisation and grade of the geological domain.

Installation of a new fine grind and flotation circuit was completed in the second half of 2018. In 2021, mining commenced at the Golden Delicious satellite pit using open cut mining methods. A new higher-grade and shallower orebody, Frankie, was accessed by year-end 2021

Tropicana

Tropicana comprises a series of open pits and an underground mine located 200km east of Sunrise Dam and 330km east-northeast of Kalgoorlie in Western Australia.

Overview and Locality

Tropicana is a joint venture between AngloGold Ashanti Australia Ltd (70%), which manages the operation, and Regis Resources Ltd (30%).

Open pit and underground mining is carried out by Macmahon under an alliance contract. Open pit mining uses conventional drill and blast and load and haul methods, while underground mining uses jumbo development and mechanised open stoping. Since start-up, ore has been sourced from the Tropicana, Havana, Havana South and Boston Shaker pits. From 2021-2023 the Boston Shaker pit will be the main source of open cut ore while a major cutback of the Havana pit is carried out. Open pit material will be supplemented by approximately 1.2 Mtpa of ore mined from the Boston Shaker underground mine, and stockpiles.

The Tropicana processing plant has achieved a throughput capacity of between 8-9 Mtpa following several upgrades, including the installation of a second ball mill. The processing plant comprises a three-stage crushing circuit, inclusive of energy-efficient high-pressure grinding rolls, followed by conventional ball mill grinding and CIL recovery. Tropicana’s infrastructure includes a gas-fired power station, sealed airstrip, workshops, two borefields, a tailings facility and a modern village complex.

 

Overview and Locality

Tropicana is a joint venture between AngloGold Ashanti Australia Ltd (70%), which manages the operation, and Regis Resources Ltd (30%).

Open pit and underground mining is carried out by Macmahon under an alliance contract. Open pit mining uses conventional drill and blast and load and haul methods, while underground mining uses jumbo development and mechanised open stoping. Since start-up, ore has been sourced from the Tropicana, Havana, Havana South and Boston Shaker pits. From 2021-2023 the Boston Shaker pit will be the main source of open cut ore while a major cutback of the Havana pit is carried out. Open pit material will be supplemented by approximately 1.2 Mtpa of ore mined from the Boston Shaker underground mine, and stockpiles.

The Tropicana processing plant has achieved a throughput capacity of between 8-9 Mtpa following several upgrades, including the installation of a second ball mill. The processing plant comprises a three-stage crushing circuit, inclusive of energy-efficient high-pressure grinding rolls, followed by conventional ball mill grinding and CIL recovery. Tropicana’s infrastructure includes a gas-fired power station, sealed airstrip, workshops, two borefields, a tailings facility and a modern village complex.

A Brief History

Open pit mining began during 2012 with first gold production occurring during September 2013. Underground mining began in 2019 at Boston Shaker after a positive feasibility study.

Tropicana reached the 3Moz produced milestone during the first quarter of 2020. First stoping in the Boston Shaker underground mine occurred in June 2020 and the mine achieved commercial production in September 2020. On 22 April 2021, Regis Resources acquired the 30% stake in Tropicana from IGO.